Next week, work on the reconstruction of the rainwater sewerage network in the area of Targowa Street. This is a street where there is a problem with rainwater management at large and intense rainfall.

As a result of the tender procedure, the contractor - is a company from Raczki - AQUAKOP sp. z o.o. After signing the contract, the contractors The construction site was handed over.

As part of the investment:

  • new channels, wells, drains will be installed rainwater
  • retention tank, a ZB1 retention tank (with a capacity of 324m3) together with venting, spigots and inspection wells,
  • a
  • pumping station will be installed and put into operation rainwater
  • in the
  • required places, the land,
  • collision and inoperative ones will be dismantled canals, wells and drains,
  • the
  • asphalt surface of ul. Targowa in the scope of excavations,
  • the
  • surface will also be replaced parking lots and internal roads from Trylinka to cobblestones.

The total cost of this investment is almost 1.5 million zlotys.

The construction site has been handed over to the contractor. The company is preparing to start work. These, should start next week (after 26 October 2026).

According to the contractor, the change in traffic organization, introduced for the duration of the works, should be in force until the end of December.

We will keep you informed about progress, stages and difficulties on an ongoing basis. It is worth following the elk.pl service and Facebook profile of the City Hall Ełk.