02 January 2018, Author: Cezary Wenda

I ended up upgrading drainage in Kościuszko Street, the section from ul. The Slovak Republic ul. Orzeszkowej. The cost of the investment is 376 thousand. zł.

The investment was based on the execution of the renovation of an existing concrete channel of the rainforest in the ul. Kosciuszko in Elk. While the work has been carried out trenchless.

You have completed the following work: restoration of rain channels and wells rainy, reconstruction of the water connections, recreating the paving bitumen roadway and adjacent sidewalks in terms of damage, restoring green areas after ongoing construction

Contractor was the company P.H.U. "AKWA" j. Bishop. S. Shepherd SP. j. from Zabrze.
The total cost of the investment is 376,371.39 €.