Preparations for the reconstruction of UL. Polish Army. There will be obstacles to traffic flow
24 May 2019, Author: Paweł Butwiłowski, admin
Started Already works related to the reconstruction of the Polish Army Street in Ełku on the stretch From the intersection with UL. Kościuszko to ul. Mickiewicz and the execution of the bay "Active" pedestrian crossing in the vicinity of the Army building Polish 62 and 68.
Currently Preparatory work is underway. The former town park was undressed In the strip dividing the Polish Army street (next to the church NSJ). Off road is a piece of inner lane running along Get.
In The first days of June, a movement organisation will be introduced to Envisaged closure for the movement of WP Street section from Zamkowej Street to the street Kościuszko (road from the ECK).
Drivers We ask for your understanding, to pay attention to the road marking and to maintain Particular caution. Any subsequent changes in the organisation of Traffic and Citizens will be kept informed.
Reconstruction of the Polish Army street is necessary due to the Traffic collisions, increasing each year the movement of cars and applications and attention of the inhabitants. Therefore, the elk Government decided to modernise the The next episode of UL. Polish Army. Investment will improve safety, Smooth traffic and the functioning of bus communication.
More about investment
Length Ul. The Polish Army, which is reconstructed, is about 515 MB, including Intersection of the streets of Armia Krajowa (length approx. 90 MB) and Zamkowej Street (length approx. 75 MB). The intersection is to be equipped with a signalling Luminous.
Reconstruction is subject to a two-way section with a straight forward with additional Turn left and right in the intersection area.
Rebuilding The construction of rainwater sewer, construction of street lighting, execution of Water supply network and sanitation system.
In The scope of the roadworks will be:
· Execution Paving, bus bays with stone cubes, downhill Concrete paving, cycling path with bituminic colour Red
· Setting Stone curbs and concrete edged edges,
· Execution Motion safety devices,
· Execution Vertical and horizontal markings,
· Execution "Active" pedestrian crossing in the vicinity of the Polish Army building 68,
· Execution Traffic lights at the intersection of Zamkowej Street, Armia Krajowa, army Polish
· Rebuilding Sections of colliising Underground networks: electricity grids, infrastructure Gas network, District heating network.
General Contractor of the works is the road works company in Ełku Sp. z o.o.
Planned Completion of all works is 15.11.2019 R.
- News (3142) »
- Events happening in Ełk (1207) »
- Education (384) »
- Videos from the series Safe Elk (9) »
- Videos of the series happens in ełk (29) »
- Physical Culture Development Fund (1) »
- Investments (186) »
- Invest - aktualności (115) »
- Invest - projekty inwestycyjne (24) »
- Invest - tereny inwestycyjne (2) »
- About Coronavirus (97) »
- Culture (510) »
- In memory (9) »
- White Lily Award Winners (12) »
- NATO in Masuria (11) »
- Awards and distinctions for Ełk (25) »
- Awards and scholarships (34) »
- Deliberations of the Elk City Council (38) »
- Ngos (307) »
- Aid to Ukraine (54) »
- Improving the energy efficiency of buildings (1) »
- Clean Air Priority Programme (2) »
- Government Local Government Roads Fund (6) »
- Government Local Investment Fund (10) »
- Government Program for the Reconstruction of Monuments (2) »
- Revitalization (51) »
- Entertainment (670) »
- Anniversaries and celebrations (141) »
- Sport (347) »
- Obstructification and changes in traffic organisation (63) »
- Obstructification and change of traffic organisation (63) »
- International cooperation (16) »
- Adopt an Ełk dog (4) »
- Tasks carried out from the state budget or from state special purpose funds (1) »
- Green transport (2) »