News

Author: M.S./ (ZI) | Publish date: 29 June 2023

Thermomodernization of another school facility in Ełk

29 June 2023, Author: M.S./ (ZI)

Further thermo-modernization works in the Ełk school facility, the central heating installation will be replaced in SP7 and the EKOLUDKI Kindergarten. The investment is co-financed from EU funds.

A contract was concluded with the contractor for works consisting in reconstruction of central heating installations, as well as installation mechanical ventilation of the school's gymnasium, as part of thermal modernization building of Primary School No. 7 at Kilińskiego Street. The scope of work includes: also the reconstruction of central heating in the EKOLUDKI Kindergarten, which is part of the school facility.

The reconstruction includes the installation of a central heating from the existing substation and covers all segments school facility with kindergarten.

Construction works will be carried out in an active facility School. Interior work in spaces used by children will be conducted during the holiday season and free from classes.

Planned date of work: by 14.10.2023

The cost of works in the SP7 building: PLN 1,079,152.58, of which the co-financing amounts to PLN 781,509.14.

The cost of works in the building of the EKOLUDKI Kindergarten: PLN 158,570.35, of which the co-financing amounts to PLN 134,626.23.

The investment is carried out as part of the project entitled. "Thermomodernization of public buildings – SP7, SP4, Ekoludki" from co-financing from the Regional Operational Programme of the Warmian-Warmian Voivodeship – Mazurski for the years 2014-2020, co-financed from European funds Regional Development Fund.

The co-financing of the entire project is 7 048 824,95 PLN.