News

Author: M.S./ (ZI) | Publish date: 26 September 2023

Modernization of another street in Zatorze

26 September 2023, Author: M.S./ (ZI)

The President of Ełk concluded a contract with the contractor for reconstruction of Malmeda Street in the Zatorze housing estate. The work will be carried out to the end Year. The value of the contract is over PLN 296,000.

Mayor of Ełk Tomasz Andrukiewicz signed a contract with the contractor for the reconstruction of Malmeda Street in the Zatorze housing estate. In As part of the reconstruction, the existing one will be removed on a section of approx. 260 m of street bituminous surface and new road surface in two layers: asphalt concrete binding layer and concrete wear layer asphalt after prior adjustment of existing manholes, sewage wells, rainwater, sanitary sewage and street drains.

Agreement It provides for the demolition of approx. 47 m of the existing pavement and the execution of demolished ones elements as new, thanks to which a pedestrian route will be created on the indicated section with a concrete paving surface.

Cost investment: PLN 296,037.88

Deadline for work: 28.12.2023 r.