News

Author: Tomasz Walczuk | Publish date: 30 August 2024

Schools and kindergartens are ready to welcome students after renovations

30 August 2024, Author: Tomasz Walczuk

With the end of the summer holidays, renovation works and investment in municipal kindergartens and primary schools. Total cost of these activities amount to PLN 943,530 – over PLN 320,000 more than in the year Last. Thanks to the work carried out, which included, among m.in, refreshing or replacement of worn elements, urban facilities will ensure that the conditions for learning and development.

Due to the holiday season in July and August in the city's renovation works and investment tasks were carried out in kindergartens and schools. The total cost of the renovations and investments is PLN 943,530, including:

Urban Kindergarten "Perełka"

Replacement of windows in the hall and bathroom

Replacement of external doors to the corridor kitchen block

Leak repair water system

Painting of rooms, cloakrooms, bathrooms

Terracotta lining of the stairs external to the basement

The playground at Primary School 2 made in as part of the Local Initiative

Urban Kindergarten "Forget-me-not"

Renovation of two bathrooms with rooms

Urban "Świetlko" Kindergarten

Renovation of the bathroom on the ground floor

Small works done in your own in terms of

Urban Kindergarten "Little Explorers"

Renovation of the multimedia room on the low ground floor (after flooding the hall)

Renovation of classroom No. 4 at Floor

Renovation of the bathroom next to room 4

Reclamation of the garden substrate, construction of the stage at the amphitheatre, purchase and installation of 6 garden toys – made in as part of the Local Initiative

Urban Kindergarten "Sunny Eight"

Renovation of the kindergarten corridor, in including: floor replacement, widening of the corridor space,

Replacing the substrate in offices Therapeutic

School Primary No. 1

Construction of an outdoor gym in as part of the Local Initiative

Installation of the power reduction device Passive

Renovation of the classroom and office

Renovation of the parquet floor in the hall gymnastics

Replacement of the surface with stone in within fitness

School Basic No. 2

Painting classrooms

Replacement of electrical installation and Lighting

Painting the auditorium, laying the panels on the Floor

School Primary No. 3

Painting of railings, stands on Bikes

Painting and Puttying in 10 classrooms, basement, corridor C, students' toilets, cloakroom on the school playground

Replacement of fencing spans with Playground

Replacing mosquito nets in the kitchen

School Primary No. 4

Renovation of the gymnasium

Replacement of doors in the gymnasium

Securing accounts in the gym

Replacing a door in a room PE teacher training

Replacement of the floor in the common room school and computer lab

Maintenance of the surface on the pitch Orlik

Sanding the parquet of a small hall gymnastics

Painting of changing rooms, toilets and separation of the warehouse on the Orlik pitch

Painting the corridor in the cloakroom School

Painting room 204

Arrangement of panels in the superintendent's office

Ongoing renovation of the kitchen (window in the potato storage, chute for potatoes, new lid)

School Primary No. 5

Painting the basement of the building, painting classrooms, corridors and staircases on each floor of the school

façade repair, demolition ceramic floors and tiles, the application of a new structure on the walls and horizontal surfaces

Schools Primary No. 7

Amendments after thermal modernization – windows in the gymnasium, roof, walls

Classroom renovation, painting the main hall, the common room, corridors next to the gym, the hall in pavilion A on the ground floor

Installation of air conditioning in room B23

School Basic No. 9

Replacing the floor covering in two classrooms

Replacing the floor with panels vinyl in two classrooms

Renovation of two bathrooms for students

Team Sports Schools

Welds were made on the roller track

The total cost of these activities is PLN 943,530 – over PLN 320,000 more than in the previous year (the amount of expenditure for this purpose in the 2023 was about PLN 620,000).