News

Author: Mateusz Gałęski | Publish date: 29 April 2025

Reconstruction of Słowackiego Street - change of traffic organization

29 April 2025, Author: Mateusz Gałęski

Immediately after the long weekend in May, works related to the reconstruction of the road and underground networks on Juliusza Słowackiego Street will begin. Therefore, changes in traffic organization will be introduced. To minimize the difficulties, the works will be carried out in stages.

At the beginning of May, right after the long weekend, the works will begin related to the reconstruction of the road and underground networks on Juliusza Słowackiego Street in Ełk. Therefore, changes in traffic organization will be introduced.

In order to minimize the inconvenience, the works will be carried out in stages. The reconstruction has been planned so that residents, suppliers and services municipal authorities could - as far as possible - move on the street at all times duration of the works.


Stage 1

  • Close section of Słowackiego Street from Armii Krajowej Street to building No. 11A.
  • On the rest of the street Traffic will take place in two directions.
  • Entry and exit to Mickiewicza Street will be possible only to a limited extent (turn into law).
  • Pedestrian traffic will be maintained — access to the buildings will be provided.
  • Deliveries to shops and access to the property will still be possible.

Stage 2

  • Close section from building No. 11A to building No. 3.
  • On the other Two-way traffic will be maintained in parts of Słowackiego Street.

Stage 3

  • Exclusion from traffic section from building No. 3 to Mickiewicza Street.
  • On the section from ul. Armii Krajowej will still be allowed to drive in both directions.

We will keep you updated on progress and changes. We apologize for the and please be careful in the area of the works.